|
Construction Schedule
Back to Neighborhood Page
Below please find a list of
upcoming construction activities. For more information please join the
School's DC
Neighbors Listserv.
For construction related
questions and concerns, please call 202-537-2415.
|
Wisconsin Avenue Structure Schedule
for June 19, 2006 through July 7, 2006 |
| |
- Sidewalk work at the Harrison loading dock is complete.
Loading dock fencing and surrounding landscaping to be completed
week of 6/19.
- Installation of finish asphalt paving for South drive
completed on 6/13. Finish asphalt paving for North drive
rescheduled for 6/20.
- Landscaping installation of shrubs and trees surrounding
garage is substantially complete. Installation of perennial
plants, vines, and ground cover to be determined by Sidwell
School.
- Replacement of damaged portions of Wisconsin Ave. sidewalk to
be complete by 6/16.
- Sandfilter interior installations underway and to be
completed after North drive finish asphalt paving.
- Garage mechanical, electrical, and plumbing (M.E.P.) systems
are substantially complete.
- H.V.A.C. testing and balancing to be performed week of 6/19.
- Installation of steel railing and stairs is substantially
complete.
- Garage parking space line stripping is substantially
complete. Space numbers to be installed by 6/26.
- Installation of the synthetic turf field is substantially
complete.
- Lowering of trellis level fence complete. Field level fencing
to be complete by 6/20.
- Field scoreboard installed on 6/15. Electrical connections to
scoreboard and painting of support posts to be complete by 6/20.
- The parking garage and B&G offices will be substantially
complete by 6/30/2006. Punch list items to be complete by
7/15/2006.
|

Click here for more Wisconsin Avenue Structure photos |
|
Middle School Schedule
for June 20 through July
4, 2006 |
| |
Concrete
Infills at the Renovation
Form & place curb @ 37th St
Continue finishing operations
Form & place concrete steps @ 37th St.
Form & place Cascade
Demobilize
Sitework
Bring Wetlands to grade
Backfill structure
Abandon existing water line in 37th Street
Abandon existing sanitary line in 37th Street
Complete backfill @ wetlands site walls
Complete site demo
Install downspout boots & piping to cistern tank
Install sidewalk, curb & gutter @ 37th St.
Mechanical/Plumbing
Set the Air Handler Unit (AHU-2) at the Renovation. This will require
the
closure of 37th Street on 6/24/06.
Test plumbing waste, domestic water, HVAC piping
Continue MEP piping, plumbing, & equipment connections in basement
Install duct work on all Levels
Install boiler breaching & stacks
Complete hook up of Cooling Towers
Install all chase/shaft duct work and piping
Install control conduit
Fire seal all shaft wall & floor penetrations
Install hangers in the Renovation
Complete duct work in the Addition
Install HVAC piping, plumbing in the Renovation
Install exhaust fans and dampers in Solar Chimneys
Electrical
Connect MCC equipment
Conduit installation on Levels B, 1 ,2 ,3 of both structures
Connect Switchgear
Complete the construction of the duct bank to Wannan Gym
Complete duct bank to pull box tie-in
Install conduit in shafts
Install wiring in exterior walls
Complete electrical rough-in at the RenovationConnect elevator power
Fire seal all shaft wall & floor penetrations
Install temporary lighting in the Renovation
Install telephone home runs for elevator
Roofing
Begin roof installation at the Addition
Frame parapets
Begin roof installation at the Renovation
Flash cooling tower curbs
Flash skylights
Install membrane on Solar Chimneys
Install roof on Stair # 2
Demolition
Complete demo of the Renovation
Cut edge of floor at the Renovation, Level 3
Drywall/Framing
Complete Solar Chimneys
Layout walls at the Renovation
Install metal studs Level 1, 2 & 3
Complete shaft & chase framing & drywall
Install metal studs at exterior walls
Install metal studs at the Renovation, Levels 1,2,3
Construct window wall framing
Wetlands
Install piping & equipment at the Reuse Tank
Begin piping to wetlands
Install pump enclosures in wetlands
Begin stone work wetlands
Set stone cap at 37th St.
Install sand filter
Install deep well structure in pond
Install wetlands liner
Masonry
Install masonry on north/east walls
Install face brick on South wall
Steel Products Complete framing at the roof of the Renovation for
AHU-2
Install end wall framing & panels at the Cooling Tower
Install Stair # 2
Install stair rails at the basement
Install bench supports
Install steel at the Renovation framing
Install steel supports at the building edge
Sprinkler
Complete sprinkler on Levels 1-3
Install risers in stairs
Install sprinkler piping at the Library ceiling
Install sprinkler piping in the Renovation |

Click here for more Middle School photos
See drawings of the new Middle School and
read more about this project on the
KieranTimberlake website. |
| |
Back to Neighborhood page
Last updated
06/22/2006
|